Free change order template with the math done

This change order template adds and removes work and works out the new contract total and finish date for you. Both of you sign before the extra work starts. Free, no sign-up.

Your business

Project and customer

Project

Contract amount

Net total of earlier signed change orders. Use a minus for credits.

Contract before this change: $0.00

Work added and removed

Add labor and materials for new work. Tick "Removes work" for anything taken out or supplied by the customer; it's subtracted as a credit.

$0.00

Added $0.00 · Removed $0.00 · This change +$0.00

Pricing the extra work? Use the markup calculator.

Schedule

days

Use a minus if the job gets shorter.

Signatures

The PDF has signature lines for you and the customer. Have the customer sign before the extra work starts.

Customer signature (sign on screen)
More optionsReason for the change, contract # and date, tax, terms, photos, logo

Reason

Contract

Tax and terms

%

Applied to the net change.

Logo

Logo

PNG or JPG. Stays on your device.

Your business

Customer

Photos

Photos

Up to 4 photos, printed on page 2 of the PDF. They stay on your device.

Your business

CHANGE ORDER

Date Nov 29, 2026

Customer

DescriptionQtyRateAmount
Original contract$0.00
This change+$0.00
New contract total$0.00

Schedule change

0 days

Terms

Added work is billed with the next progress payment. Work in this change order starts after both sides sign.

Made with Hitch Invoice

Contractor signature
Customer signature

Document style

Your color

Every style prints the same details. Your pick is saved for your next document.

Draft saved on this device.

New contract total

$0.00

Last updated: . Sources: Change order math done in your browser.

Change order example for construction: rot found mid-job

A remodeler's contract for a hall bathroom was $18,400, and two earlier change orders added $650. Under the old tub they find a rotted subfloor, and the customer decides to supply their own vanity.

LineAmount
Original contract$18,400.00
Earlier change orders+$650.00
Add: replace rotted subfloor, 40 sq ft+$780.00
Add: GFCI outlet by vanity+$185.00
Remove: vanity (customer supplied)-$420.00
This change order+$545.00
New contract total$19,595.00

The schedule moves 2 days, from Dec 16 to Dec 18, 2026.

What a change order must include

How to price and write a change order

  1. Tap Start from my saved estimate, or enter the customer, project and original contract amount.
  2. Enter the total of earlier signed change orders.
  3. Add the new work as labor and materials lines, priced from your cost plus markup.
  4. Add removed work and tick Removes work, so it's subtracted as a credit.
  5. Enter the schedule change in days and the current finish date.
  6. Under More options, write the reason, the contract number and your terms.
  7. Download the PDF, and have the customer sign before you start.

When to require a change order

SituationChange order?
Customer adds or upgrades anythingYes, before you start it
Hidden damage found (rot, old wiring)Yes, with photos
Customer removes work or supplies materialsYes, as a credit
A question about the plans (RFI)Only if the answer changes the work
You fix your own mistakeNo

Keep each signed change order with the contract, numbered CO-1, CO-2 and so on, so your change order log is the stack of signed forms.

Download a blank template: change order template Word, Excel or PDF

Prefer a paper change order form for construction? Download a free change order template. No email needed.

Questions contractors ask

How do you write a change order?

Name the project and the original contract, list the work added and removed with prices, show the original amount, earlier change orders and the new contract total, give the schedule change in days and the reason, then have both sides sign. The change order template above does the math and makes the PDF.

What is a change order form?

A change order form is a short written agreement that changes the scope, price or schedule of a signed contract. It protects you and the customer: nobody argues later about what extra work was asked for or what it costs.

What's the difference between an RFI and a change order?

An RFI (request for information) asks a question about the plans or specs, like which tile goes where; it does not change the price. A change order changes the scope, price or schedule and needs both signatures. An RFI answer often leads to a change order when it adds or removes work.

How do I price a change order?

Price it the same way as the original job: your labor hours and materials at cost, plus your markup for overhead and profit. Removed work becomes a credit at the price it had in the contract. The markup calculator helps you set the price.

Can I start extra work before the change order is signed?

It is safer not to. Without a signed change order you may have trouble getting paid for the extra work, and some states require written change orders on home improvement contracts. This is general information, not legal advice.